Draw the resource loading graph for each schedule in Exercise 5.6. Exercise 5.6 Schedule the project in

Question:

Draw the resource loading graph for each schedule in Exercise 5.6.

Exercise 5.6

Schedule the project in Exercise 5.3 using each of the following heuristics: CAF, LS, ES, LC, EC, TS, CRD, and ACTIM. What is the shortest project duration obtained? Which heuristics yield that shortest project duration?

Exercise 5.3

Use the minimum totals lack (Min TS) heuristic to schedule the resource-constrained project. If a tie occurs, use minimum activity duration to break the tie.

Units of resource type 1 available \(=10\)

Units of resource type 2 available \(=15\)