Schedule the project in Exercise 5.3 using each of the following heuristics: CAF, LS, ES, LC, EC,
Question:
Schedule the project in Exercise 5.3 using each of the following heuristics: CAF, LS, ES, LC, EC, TS, CRD, and ACTIM. What is the shortest project duration obtained? Which heuristics yield that shortest project duration?
Exercise 5.3
Use the minimum totals lack (Min TS) heuristic to schedule the resource-constrained project. If a tie occurs, use minimum activity duration to break the tie.
Units of resource type 1 available \(=10\)
Units of resource type 2 available \(=15\)
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Systems Principles And Applications
ISBN: 272859
2nd Edition
Authors: Adedeji B. Badiru
Question Posted: