Suppose it is known that the duration of a project has a triangular distribution with a lower

Question:

Suppose it is known that the duration of a project has a triangular distribution with a lower limit of 24months, an upper limit of 46months, and a mode of 36months.

Find the probability that the project can be completed in 40months or less.