Suppose it is known that the duration of a project has a triangular distribution with a lower
Question:
Suppose it is known that the duration of a project has a triangular distribution with a lower limit of 24months, an upper limit of 46months, and a mode of 36months.
Find the probability that the project can be completed in 40months or less.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 100% (1 review)
Answered By
Ashington Waweru
I am a lecturer, research writer and also a qualified financial analyst and accountant. I am qualified and articulate in many disciplines including English, Accounting, Finance, Quantitative spreadsheet analysis, Economics, and Statistics. I am an expert with sixteen years of experience in online industry-related work. I have a master's in business administration and a bachelor’s degree in education, accounting, and economics options.
I am a writer and proofreading expert with sixteen years of experience in online writing, proofreading, and text editing. I have vast knowledge and experience in writing techniques and styles such as APA, ASA, MLA, Chicago, Turabian, IEEE, and many others.
I am also an online blogger and research writer with sixteen years of writing and proofreading articles and reports. I have written many scripts and articles for blogs, and I also specialize in search engine
I have sixteen years of experience in Excel data entry, Excel data analysis, R-studio quantitative analysis, SPSS quantitative analysis, research writing, and proofreading articles and reports. I will deliver the highest quality online and offline Excel, R, SPSS, and other spreadsheet solutions within your operational deadlines. I have also compiled many original Excel quantitative and text spreadsheets which solve client’s problems in my research writing career.
I have extensive enterprise resource planning accounting, financial modeling, financial reporting, and company analysis: customer relationship management, enterprise resource planning, financial accounting projects, and corporate finance.
I am articulate in psychology, engineering, nursing, counseling, project management, accounting, finance, quantitative spreadsheet analysis, statistical and economic analysis, among many other industry fields and academic disciplines. I work to solve problems and provide accurate and credible solutions and research reports in all industries in the global economy.
I have taught and conducted masters and Ph.D. thesis research for specialists in Quantitative finance, Financial Accounting, Actuarial science, Macroeconomics, Microeconomics, Risk Management, Managerial Economics, Engineering Economics, Financial economics, Taxation and many other disciplines including water engineering, psychology, e-commerce, mechanical engineering, leadership and many others.
I have developed many courses on online websites like Teachable and Thinkific. I also developed an accounting reporting automation software project for Utafiti sacco located at ILRI Uthiru Kenya when I was working there in year 2001.
I am a mature, self-motivated worker who delivers high-quality, on-time reports which solve client’s problems accurately.
I have written many academic and professional industry research papers and tutored many clients from college to university undergraduate, master's and Ph.D. students, and corporate professionals. I anticipate your hiring me.
I know I will deliver the highest quality work you will find anywhere to award me your project work. Please note that I am looking for a long-term work relationship with you. I look forward to you delivering the best service to you.
3.00+
2+ Reviews
10+ Question Solved
Related Book For
Project Management Systems Principles And Applications
ISBN: 272859
2nd Edition
Authors: Adedeji B. Badiru
Question Posted:
Students also viewed these Business questions
-
1. Perform a PERT analysis of the following project and find the probability of finishing the project between 16 and 20 days inclusive. 2. Suppose it is known that the duration of a project is...
-
Suppose it is known that the duration of a project is uniformly distributed between 24 and 46months. Find the probability that the project can be completed in 40months or less.
-
QUIZ... Let D be a poset and let f : D D be a monotone function. (i) Give the definition of the least pre-fixed point, fix (f), of f. Show that fix (f) is a fixed point of f. [5 marks] (ii) Show that...
-
1. Johnathan's utility for money is given by the exponential function: U(X)-4-4*100). a. Based on his utility function, what is his risk-odds for the S+/-1 deal, r($1)? b. Is Johnathan a deltaperson?...
-
Consider the network setup in Figure 4.22. Suppose that the ISP instead assigns the router the address 24.34.112.235 and that the network address of the home network is 192.168. 1124. a) Assign...
-
On 1 July 20X2, King Ltd. purchased $500,000 bonds of Princess Inc. at par. The bonds pay 6% interest annually on June30. The bonds mature on30June20X9. King has a June30year-end.At30June 20X3, King...
-
A local electronics company has several production facilities scattered throughout the midwestern United States. The company is looking to establish a distribution center to ship its products to Best...
-
Corporate bonds issued by Johnson Corporation currently yield 8 percent. Municipal bonds of equal risk currently yield 6 percent. At what tax rate would an investor be indifferent between these two...
-
25 Morton uses the moving average flow assumption. On January 1, there were 180 units on hand and the total inventory cost was $900. On January 10, 40 more units were purchased at a cost of $6 per...
-
You are given the following project data: If the PERT time estimates for each activity are defined as \[ \begin{aligned} & a=t-0.3 t \\ & m=t \\ & b=t+\sqrt{t} \end{aligned} \] find a deadline,...
-
Answer the following questions using the tabulated project data. a. There is a penalty of $3,000/day beyond the normal PERT duration. Perform a crashing analysis to compare total normal cost to total...
-
Draw resonance structures for each of the following compounds: a. b. c. d. e. f. g. h. i. j. N.
-
Assume an organic compound has a partition coefficient between water and ethyl acetate equal to 8.12. If there are initially 7.10 grams of the compound dissolved in 75.0 mL of water, how many grams...
-
Berger Paint Pakistan limited produces three types of joint products, S ilver paint, G olden paint and D iamond paint. During March, 2020, the following information was recorded : Particulars Silver...
-
Choose an industry in which you are interested in working. How is that industry trending? What internal and external factors may affect the direction of the organization? For your initial post,...
-
show all work and Computations and if favorable or unfavorable. Standard Cost Data per 1 Unit Quantity Price Direct Labor 2 hrs $4.00/hr Actual Data: Units produced 20 20 Direct Labor 30 hrs; total...
-
4. A petroleum company is considering the expansion of its one unloading facility at its Australian refinery. Due to random variations in weather, loading delays, and other factors, ships arriving at...
-
The estimated demand curve for popsicles on a particular beach on a sunny summer day is given by Q = 130 3.5p, where p is measured in dollars. What is the predicted quantity if p = $ 2.00. If the...
-
Activator rod AB exerts on crank BCD a force P directed along line AB. Knowing that P must have a 100-N component perpendicular to arm BC of the crank, determine (a) The magnitude of the force P, (b)...
-
Eye Deal Optometry leased vision - testing equipment from Insight Machines on January 1 , 2 0 2 4 . Insight Machines manufactured the equipment at a cost of $ 2 0 0 , 0 0 0 and lists a cash selling...
-
help! ee all photos + Add to o e D C N X Edit & Create Share Table of Contents No sales to an individual customer accounted for more than 10% of revenue during any of the last three fiscal years. Net...
-
Business law A person may have the liability of a partner even though no partnership exists True False
Study smarter with the SolutionInn App