Answer the following questions using the tabulated project data. a. There is a penalty of $3,000/day beyond
Question:
Answer the following questions using the tabulated project data.
a. There is a penalty of $3,000/day beyond the normal PERT duration. Perform a crashing analysis to compare total normal cost to total crash cost. First crash only the critical activities; then crash all activities.
b. Find the probability that the total lateness penalty will be less than $3,000.
c. Find the probability that the total lateness penalty will be $3,000 or less.
d. Find the probability that the total lateness penalty will be greater than $3,000.
e. Find the probability that the total lateness penalty will be less than $9,000.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Systems Principles And Applications
ISBN: 272859
2nd Edition
Authors: Adedeji B. Badiru
Question Posted: