The table and graph that follows represent a contractors overdraft requirements for a project. Complete the table

Question:

The table and graph that follows represent a contractor’s overdraft requirements for a project. Complete the table shown for costs, markup, total worth, retainage, and pay received. Retainage is 10%, markup is 10%, and interest is 1% per month. The client is billed at the end of the month. Payment is received at the end of the next month and to be deposited in the bank on the first of the following month.

image text in transcribed