Use the approach presented to compute the project network complexity for the data in Exercise 5.3. Exercise
Question:
Use the approach presented to compute the project network complexity for the data in Exercise 5.3.
Exercise 5.3
Use the minimum totals lack (Min TS) heuristic to schedule the resource-constrained project. If a tie occurs, use minimum activity duration to break the tie.
Units of resource type 1 available \(=10\)
Units of resource type 2 available \(=15\)
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Systems Principles And Applications
ISBN: 272859
2nd Edition
Authors: Adedeji B. Badiru
Question Posted: