The standard labour cost of a component is 5 and a standard deviation of 20p has been
Question:
The standard labour cost of a component is £5 and a standard deviation of 20p has been estimated.
a. Calculate the 2% control limits.
b. Ina period the output was 480 units and the labour cost was exactly on the upper 2% limit. What was the actual labour cost in the period and what was the labour cost variance?