An engineering firm operates a job costing system. Production overhead is absorbed at the rate of $8.50
Question:
An engineering firm operates a job costing system. Production overhead is absorbed at the rate of $8.50 per machine hour. In order to allow for nonproduction overhead costs and profit, a mark up of 60 per cent of prime cost is added to the production cost when preparing price estimates.
The estimated requirements of job number 808 are as follows:
The estimated price notified to the customer for job number 808 will be:
(a) $22256
(b) $22851
(c) $23446
(d) $24160 (2 marks)
CIMA — Management Accounting Fundamentals
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: