One of the building contracts currently engaged in by a construction company commenced 15 months ago and
Question:
One of ·the building contracts currently engaged in by a construction company commenced 15 months ago and remains unfinished. The followi ng information relating to wor k on the contract has been prepared for the year just ended.
As soon as materials are delivered to the site. they are charged to the Contract Account. A record is also kept of materials as they are actually used on the contract. Periodically a stock check is made and any discrepancy between book stock and physical stock is transferred to a General Contract Mater ials Discrepancy Account. This is absorbed back into each contract.
currently at a rate of 0.4% of materials booked. The stock check at the end of the year revealed a stock shortage of £4.000.
In addition to the direct charges listed above. general overheads of the company are charged to contracts at 5% of the value of wor k certified.
General overheads of £13.000 had been absorbed into the cost of work completed at the beginning of the year.
It has been estimated that further costs to complete the contract will be £215.000. This estimate includes the cost of materials on site at the end of the year just finished. and also a provision for rectification .
Required :
(a) Explain briefly the distinguishing features of contract costing.
(b) Determine the profitability of the above contract. and recommend how much profit (to the nearest (000) should be taken for the year just ended. (Provide a detailed schedule of costs.)
[c] State how your recommendation in
(b) wou ld be affected if the contract price was £3,500,000 (rather than £2,100.000) and if no estimate has been made of costs to completion