3-26. A small plant has been constructed and the costs are known. A new plant is to...

Question:

3-26. A small plant has been constructed and the costs are known. A new plant is to be estimated with the use of the exponential (power sizing) costing model. Major equipment, costs, and factors are as shown in Table P3-26. (Note MW = 106 Watts.) If ancillary equipment will cost an additional $200,000, find the cost for the proposed plant. (3.4)