36. Find the average time per unit required to produce the first 30 units, if the slope...
Question:
36. Find the average time per unit required to produce the first 30 units, if the slope parameter of the learning rate is 92% and the first unit takes 460 hours.
(a) 330.693
(b) 305.5404
(c) 245
(d) 347.3211