5-37. The city of Oak Ridge is considering the construction of a four kilometer (km) greenway walking

Question:

5-37. The city of Oak Ridge is considering the construction of a four kilometer (km) greenway walking trail. It will cost $1,000 per km to build the trail and $300 per km per year to maintain it over its 20-year life. If the city’s MARR is 7% per year, what is the equivalent uniform annual cost of this project? Assume the trail has no residual value at the end of 20 years. (5.5)

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Engineering Economy

ISBN: 9780134870069

17th Edition

Authors: William Sullivan, Elin Wicks, C Koelling

Question Posted: