7. 11.27 A 100,000 barrel per day (BPD) fractionation tower cost $1.2 million in 2010. Use the...

Question:

7. 11.27 A 100,000 barrel per day (BPD) fractionation tower cost $1.2 million in 2010. Use the chemical engineering plant cost index (CEPCI) to estimate the cost for a 450,000 BPD plant cost. The index (annual value) is now 607.0, and the exponent in the cost-capacity equation is 0.67.