Improvements at a Harley-Davidson Plant are estimated to be $7.8 million. Construction is expected to take three
Question:
Improvements at a Harley-Davidson Plant are estimated to be $7.8 million. Construction is expected to take three years. What is the future worth of the project in year 3 at an interest rate of 6% per year compounded quarterly, assuming the funds are allocated
(a) completely at time 0, and
(b) equally at the end of each year?