Pollution control equipment for a pulverized coal cyclone furnace is expected to cost $190,000 two years from
Question:
Pollution control equipment for a pulverized coal cyclone furnace is expected to cost $190,000 two years from now and another $120,000 four years from now. If Monongahela Power wants to set aside enough money now to cover these costs, how much must be invested at an interest rate of 8% per year compounded quarterly?