With an installed capacity in excess of 11,000 MW, the Belo Monte dam complex on the Xingu

Question:

With an installed capacity in excess of 11,000 MW, the Belo Monte dam complex on the Xingu River in Brazil will be the world’s third largest hydroelectric dam. The project is expected to cost $16 billion and will begin producing electricity upon completion by the end of 2019 after the 5-year construction period. Even though the dam will provide clean energy for millions of people, environmentalists are sharply opposed. They say it will devastate wildlife and the livelihoods of 40,000 people who live in the area to be flooded.

Assume that the funding will occur evenly over the 5-year construction period (i.e., $3.2 billion per year), and that the disbenefits will be $66,000 for each displaced person and $1 billion for wildlife destruction. Further, assume the disbenefits will occur evenly through the 5-year construction period and the benefits will begin in 2020 and continue indefinitely. At a discount rate of 8% per year, use the B/C ratio to determine the minimum annual benefits required to economically justify the project.

Discount Rate
Depending upon the context, the discount rate has two different definitions and usages. First, the discount rate refers to the interest rate charged to the commercial banks and other financial institutions for the loans they take from the Federal...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question