The standard cost of Product YY includes 3 hours of direct labor at $12.00 per hour. The

Question:

The standard cost of Product YY includes 3 hours of direct labor at $12.00 per hour. The predetermined overhead rate is $20.00 per direct labor hour. During July, the company incurred 3,500 hours of direct labor at an average rate of $12.40 per hour and $71,300 of manufacturing overhead costs. It produced 1,200 units.

(a) Compute the total, price, and quantity variances for labor.

(b) Compute the total overhead variance.

Fantastic news! We've Found the answer you've been seeking!