Skimpy plc is a construction company currently undertaking three large construction contracts in its South West Division.
Question:
Skimpy plc is a construction company currently undertaking three large construction contracts in its South West Division. Information relating to these three contracts for the year ended 31 October 20X9 is as follows:
Skimpy operates a local head office in the South West Division, the costs of which totalled £70,000 in the year ended 31 October 20X9. These costs are to be apportioned over the three construction contracts in the region in proportion to the wages paid.
The Plymouth contract is nearing completion and the site architect estimates that the additional costs to complete the contract will total £60,000. This sum includes an allowance for all anticipated costs including overheads and contingencies.
Required:
(a) Prepare a cost account for each of the three contracts for the year ended 31 October 20X9 and show the cost of the work completed at the end of the year. (16 marks)
(b) For each contract recommend, giving reasons, how much profit or loss should be taken for the year ended 31 October 20X9.