3 Johnson Industries received a contract to develop and produce four high-intensity long-distance receiver/transmitters for cellular telephones.
Question:
3 Johnson Industries received a contract to develop and produce four high-intensity long-distance receiver/transmitters for cellular telephones. The first took 2,000 labor hours and $39,000 worth of purchased and manufactured parts; the second took 1,500 labor hours and $37,050 in parts; the third took 1,450 labor hours and $31,000 in parts; and the fourth took 1,275 labor hours and $31,492 in parts. Johnson was asked to bid on a follow-on contract for another dozen receiver/transmitter units. Ignoring any forgetting factor effects, what should Johnson estimate time and parts costs to be for the dozen units? (Hint: There are two leaming curves-one for labor and one for parts.)