Daffy Dave's Sub Shop makes custom submarine sandwiches to order. They are analyzing the processes at their
Question:
Daffy Dave's Sub Shop makes custom submarine sandwiches to order. They are analyzing the processes at their shop. The general flow of the process is shown below. There is a separate person working at each of the steps in the process.
Daffy Dave wants to figure out the following for a typical 8-hour work day. a What is the current maximum output of the process?
b. If we add another person where would we add him or her and what is the benefit?
c. Is there a benefit if we can shift 1 minute from Bun and Meat to Order Taking? Assume we do not make the change in part b above.
d. Is there a benefit if we shift 1 minute of work from Condiments to Bagging? Assume we do not make the changes in parts b and c above.