The following table lists the components needed to assemble an end item, lead times, and quantities on

Question:

The following table lists the components needed to assemble an end item, lead times, and quantities on hand.

Item End B C D E F G H LT (wk) 1 2 3 3 1 2 1 2 Amount on hand 0 10 10 25 12 30 5 0 End Item B (2) C D (3)
E (2) F (3) G (2) E (2) H (4) E (2)

a. If 20 units of the end item are to be assembled, how many additional units of E are needed?
(Hint: You don’t need to develop an MRP plan to determine this.)

b. An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan for this part either.) LO.1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 9781260575712

14th Edition

Authors: William J Stevenson

Question Posted: