The project described in the following table is scheduled to be completed in 11 weeks. Construct a

Question:

The project described in the following table is scheduled to be completed in 11 weeks. Construct a network diagram using AOA or AON (see Example 5 for either type). Then, answer the following questions:

a. If you were the manager of this project, would you be concerned? Explain.

b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000?

Path Activity Estimated Time

(weeks)

Standard Deviation (wks.)

A C 4 0.70 D 6 0.90 B E 3 0.62 F 9 1.90

 LO.1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 9781260575712

14th Edition

Authors: William J Stevenson

Question Posted: