During 2015, Nilsen Company started a construction job with a contract price of 1,600,000. The job was

Question:

During 2015, Nilsen Company started a construction job with a contract price of €1,600,000. The job was completed in 2017. The following information is available.

image text in transcribed

Instructions

(a) Compute the amount of gross profit to be recognized each year, assuming the percentage-ofcompletion method is used.

(b) Prepare all necessary journal entries for 2016.

(c) Compute the amount of gross profit to be recognized each year, assuming the cost-recovery method is used.