During 2015, Nilsen Company started a construction job with a contract price of 1,600,000. The job was
Question:
During 2015, Nilsen Company started a construction job with a contract price of €1,600,000. The job was completed in 2017. The following information is available.
Instructions
(a) Compute the amount of gross profit to be recognized each year, assuming the percentage-ofcompletion method is used.
(b) Prepare all necessary journal entries for 2016.
(c) Compute the amount of gross profit to be recognized each year, assuming the cost-recovery method is used.