On April 1, 2019, Pine Construction Company entered into a fixed-price contract to construct an apartment building
Question:
On April 1, 2019, Pine Construction Company entered into a fixed-price contract to construct an apartment building for $6,000,000. Pine will satisfy the performance obligations in the contract over time and appropriately accounts for this contract. Information relating to the contract is as follows:
What is the amount of contract costs incurred during the year ended December 31, 2020?
a. $1,200,000
b. $1,920,000
c. $1,980,000
d. $2,880,000