In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara

Question:

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 

2021 2022 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,400,000 $3,600,000 $2,200,000 5,600,000 2,000,000 -0- 2,000,000 4,000,000 4,000,000 1,800,000 3,600,000 4,600,000

Westgate recognizes revenue over time according to percentage of completion. 


Required: 

1. Calculate the amount of revenue and gross profit to be recognized in each of the three years. 

2. Prepare all necessary journal entries for each of the years (credit “Cash, Materials, etc.” for construction costs incurred). 

3. Prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. Indicate whether any of the amounts shown are contract assets or contract liabilities. 

4. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information: 

5. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information: 

Balance Sheet
Balance sheet is a statement of the financial position of a business that list all the assets, liabilities, and owner’s equity and shareholder’s equity at a particular point of time. A balance sheet is also called as a “statement of financial...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting

ISBN: 978-1260481952

10th edition

Authors: J. David Spiceland, James Sepe, Mark Nelson, Wayne Thomas

Question Posted: