3.21. It is July 16. A company has a portfolio of stocks worth $100 million. The beta...

Question:

3.21. It is July 16. A company has a portfolio of stocks worth $100 million. The beta of the portfolio is 1.2. The company would like to use the CME December futures contract on the S&P 500 to change the beta of the portfolio to 0.5 during the period July 16 to November 16. The index futures price is 1,000, and each contract is on $250 times the index.

a. What position should the company take?

b. Suppose that the company changes its mind and decides to increase the beta of the portfolio from 1.2 to 1.5. What position in futures contracts should it take?