Question: Complete the following table. Lead time for the part is 2 weeks. The lot size is 100. What is the projected available at the end
Complete the following table. Lead time for the part is 2 weeks. The lot size is 100. What is the projected available at the end of week 3? When is it planned to release an order?

Week Gross Requirements Scheduled Receipts Projected Available 30 Net Requirements Planned Order Receipt Planned Order Release 1 20 2 65 100 3 35 4 25
Step by Step Solution
3.52 Rating (162 Votes )
There are 3 Steps involved in it
Week Gross requirements Scheduled rec... View full answer