Question: Complete the following table. Lead time for the part is 2 weeks. The lot size is 50. What is the projected available at the end
Complete the following table. Lead time for the part is 2 weeks. The lot size is 50. What is the projected available at the end of week 3? When is it planned to release an order?

Week Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release 10 1 30 50 2 25 3 10 4 10