Question: Given the following product tree, complete the MRP records for parts X, Y, W, and Z. Note that parts X and Y have specified order
Given the following product tree, complete the MRP records for parts X, Y, W, and Z. Note that parts X and Y have specified order quantities.


Z(1) Y(3) W(1) X Z(2) Part X Lead Time: 1 week Lot Size: 20 Part Y Gross Requirements Scheduled Receipts Lead Time: 2 weeks Projected Available Lot Size: 50 Part Z Lead Time: 1 week Lot Size: lot-for-lot Part W Lead Time: 1 week Week Gross Requirements Scheduled Receipts Projected Available 10 Lot Size: 400 Net Requirements Planned Order Receipt Planned Order Release Net Requirements Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release 30 1 15 20 2 10 50 90 3 15 4 10 5 15
Step by Step Solution
3.43 Rating (153 Votes )
There are 3 Steps involved in it
Part X Lead time 1 week Lot size20 Part Y Lead time 2 weeks Lot size 50 Part Z ... View full answer
Get step-by-step solutions from verified subject matter experts