1134.9. MPS parent X has planned order releases of 30 in weeks 2 and 4. Given the...

Question:

1134.9. MPS parent X has planned order releases of 30 in weeks 2 and 4. Given the following product tree, complete the MRP records for parts Y and Z. Quantities required are shown in brackets.

image text in transcribed