In problem 6.4, what percentage of time is the order actually running? In problem 6.4 An order

Question:

In problem 6.4, what percentage of time is the order actually running?

In problem 6.4

An order for 50 of a product is processed on work centers A and B. The setup time on A is 45 minutes, and run time is 5 minutes per piece. The setup time on B is 30 minutes, and the run time is 4 minutes per piece. Wait time between the two operations is 8 hours. The move time between A and B is 60 minutes. Wait time after operation B is 8 hours, and the move time into stores is 2 hours. Queue at work center A is 40 hours and at B is 35 hours. Calculate the total manufacturing lead time for the order.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Introduction To Materials Management

ISBN: 978-9386873248

8th edition

Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen

Question Posted: