In problem 6.4, what percentage of time is the order actually running? In problem 6.4 An order
Question:
In problem 6.4, what percentage of time is the order actually running?
In problem 6.4
An order for 50 of a product is processed on work centers A and B. The setup time on A is 45 minutes, and run time is 5 minutes per piece. The setup time on B is 30 minutes, and the run time is 4 minutes per piece. Wait time between the two operations is 8 hours. The move time between A and B is 60 minutes. Wait time after operation B is 8 hours, and the move time into stores is 2 hours. Queue at work center A is 40 hours and at B is 35 hours. Calculate the total manufacturing lead time for the order.