Aconstruction company spent $180,000 during the current year on a building with a contract price of $900,000.
Question:
Aconstruction company spent $180,000 during the current year on a building with a contract price of $900,000. The company estimated total construction cost at $720,000.
How much construction income will the company report under the percentage-of-completion method? (p. 498)
a. $45,000
c. $180,000
b. $144,000
d. $225,000