3.14. Given the following data, calculate the projected available balance and the planned MPS receipts. The lot

Question:


3.14. Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 200. The demand time fence is 2 weeks.

Week 1

2 3

4 Forecast 80 80 80 70 Customer Orders 100 90 50 40 Projected Available Balance 140 MPS

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Introduction To Materials Management

ISBN: 9781292162355

8th Global Edition

Authors: J. R. Tony Arnold, Chapman, Stephen N., Lloyd M. Clive

Question Posted: