A resource assigned to your project contacts you, trying to get off the team. He knows that

Question:

A resource assigned to your project contacts you, trying to get off the team. He knows that an important project in his department is going to be approved and will take place at the same time as yours. He wants to work on the other project. Under the circumstances, what should you do?

a. Release him from the team

b. Talk to the functional manager about releasing him from the team

c. Release him after he finds a suitable replacement

d. Speak with the project sponsor about releasing him from the team