A team member is not performing well on the project because she is inexperienced in database development
Question:
A team member is not performing well on the project because she is inexperienced in database development work. There is no-one else available who is better qualified to do the work. What is the BEST solution for the project manager?
a. Consult with the functional manager to determine project completion incentives for the team member
b. Obtain a new resource more skilled in this kind of work
c. Arrange for the team member to get required training
d. Allocate some of the project schedule reserve
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Leadership In Project Management Leading People And Projects To Success
ISBN: 9780991779215
2nd Edition
Authors: Mohit Arora, Haig Baronikian
Question Posted: