2. Create a weighted scoring model to determine which project to select. Assume the criteria are quality,

Question:

2. Create a weighted scoring model to determine which project to select. Assume the criteria are quality, strategic value, risk, and financials, with weights of 15%, 40%, 20%, and 25%, respectively.

Enter values for Project 1 as 90, 70, 85, and 50; Project 2 as 75, 80, 90, and 70; and Project 3 as 80 for each criterion. Use the weighted scoring model template provided on the companion Web site to create the model, calculate the weighted score, and graph the results.