6. ___________ is a technique for making cost and schedule trade-offs to obtain the greatest amount of

Question:

6. ___________ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.

A. Crashing B. Fast tracking C. De-scoping D. Parametric modeling