What is ProNet's direct labor efficiency variance for August? a. ($ 75.00 mathrm{~F}) b. ($ 232.50 mathrm{~F})
Question:
What is ProNet's direct labor efficiency variance for August?
a. \(\$ 75.00 \mathrm{~F}\)
b. \(\$ 232.50 \mathrm{~F}\)
c. \(\$ 225.00 \mathrm{~F}\)
d. \(\$ 1,350.00 \mathrm{~F}\)
ProNet Systems has budgeted 3 hours of direct labor per connector, at a standard cost of \(\$ 15\) per hour. During January, technicians actually worked 210 hours completing the 75 connectors. ProNet paid the technicians \(\$ 15.50\) per hour.