Suppose an investment project costing `100 million is expected to yield a return of `115 million after

Question:

Suppose an investment project costing `100 million is expected to yield a return of `115 million after a period of one year. If IRR = 0.08 and risk probability = 0.12, find the risk-adjusted NPV.

Is the project acceptable on these conditions? Suppose expected return increases tò125 million, will it affect the investment decision?