George, a developer on your agile project, approaches you as team coach and asks for your approval

Question:

George, a developer on your agile project, approaches you as team coach and asks for your approval to take 5 days of vacation in the next iteration. You reply:

A. “Let’s look at the backlog to see if that is a bad time before I approve it.”

B. “Based on the sustainable pace, we can only spare you for 3 days.”

C. “Bring it to the team for their decision.”

D. “You’ve earned it—approved.”