The agile team is meeting with a new member to quickly orient him to the project. He
Question:
The agile team is meeting with a new member to quickly orient him to the project. He asks, “What do you do when you are near the end of an iteration and the burndown chart doesn’t reflect the targeted progress?” The team best responds:
A. We press on with the work at hand, trying to complete the most valuable features first.
B. We put everything in high gear, working a few extra hours than normal each day to get it done.
C. We prepare for the next iteration by reducing the team velocity and adjusting how much we commit to in an iteration.
D. We have a quick swarm to determine how to adapt our process to increase our velocity and recover this iteration as much as possible.