While estimating efforts required to complete Story-17, the team determines it is more effort than Story-4 and

Question:

While estimating efforts required to complete Story-17, the team determines it is more effort than Story-4 and less effort than Story-11.

This represents what approach in estimating?

A. The delta technique B. Planning poker C. Affinity estimating D. Triangulating, or relative sizing.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: