21. A deliverable-oriented grouping of project components to organize and define the total project scope is: A.
Question:
21. A deliverable-oriented grouping of project components to organize and define the total project scope is:
A. A detailed plan B. A linear responsibility chart C. A work breakdown structure (WBS)
D. A cost accounting coding system
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Using The Project Management Maturity Model Strategic Planning For Project Management
ISBN: 978-1119530824
3rd Edition
Authors: Harold Kerzner
Question Posted: