37. The three most common types of project cost estimates are: A. Order of magnitude, parametric, and
Question:
37. The three most common types of project cost estimates are:
A. Order of magnitude, parametric, and budget B. Parametric, definitive, and top down C. Order of magnitude, definitive, and bottom up D. Order of magnitude, budget, and definitive
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Using The Project Management Maturity Model Strategic Planning For Project Management