Elements of the project that are not listed on the WBS are considered what? Choose two. A.
Question:
Elements of the project that are not listed on the WBS are considered what? Choose two.
A. Work that will be completed in a future phase of the project.
B. Exclusions from scope.
C. They are considered scope creep.
D. They are not considered part of the project.