For the above four projects, assign scores of high 3, medium 2, and low
Question:
For the above four projects, assign scores of high 3, medium 2, and low 1.
Assume the criteria are weighted Potential Return on Investment 0.3, Lack of Technological Risk 0.3, Environmental “ Friendliness ” 0.3, and Service to Community 0.1. Now which projects come out best and worst?