The cost of the entire program (1.00.00) is: a. $25K b. $66K c. $91K d. Cannot be
Question:
The cost of the entire program (1.00.00) is:
a. $25K
b. $66K
c. $91K
d. Cannot be determined Answer Questions 3–6 using the work breakdown structure shown below (numbers in parentheses show the dollar value for a particular element):
1.00.00 1.1.0 ($25k)
1.1.1 1.1.2 ($12k)
1.2.0 1.2.1 ($16k)
1.2.2.0 1.2.2.1 ($20k)
1.2.2.2 ($30k)