The PMBOKRGuide states: Project Risk has its origins in the uncertainty present in all projects. It defines
Question:
The PMBOKRGuide states: Project Risk has its origins in the uncertainty present in all projects. It defines known risks as those that have been identified and analyzed, making it possible to plan responses for those risks. Specific unknown risks cannot be managed proactively, which suggests that the project team should create a contingency plan. Describe three recommendations you would make to manage unknown risks.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Megaproject Management Lessons On Risk And Project Management From The Big Dig
ISBN: 9781118115473
1st Edition
Authors: Virginia A. Greiman
Question Posted: