This chapter refers to the use of independent auditors that were external to the project. What are
Question:
This chapter refers to the use of independent auditors that were external to the project. What are the advantages of independent audits? Describe what you believe should be the role of an independent auditor.
Independent Audits
A global accounting and consulting firm was placed on contract to validate project developed cost and schedule assessments. These periodic reports contained numerous recommendations for cost and schedule control and cost containment. In addition, audit reports were issued by independent agencies including the National Academy of Engineering, independent auditors, and state and federal audit agencies.
For instance, as claims increased dramatically during the peak years of the project from 1999 to 2003, a new protocol was established to handle these claims and changes based on the recommendations of an outside audit. An important feature of the claims and changes program was the requirement of independent audits of claims that had been conducted during the claim resolution process rather than after that process had been completed. Some examples of the findings of these reports are highlighted in Table 8.7.
Best Practices Few would dispute that independent outside audits are a necessary control mechanism for megaprojects; however, compliance with these reports is not always certain. Projects must be held accountable and demonstrate where audit recommendations are adopted, as well as where they are rejected and the reasons why the recommendations will not be implemented.
Step by Step Answer:
Megaproject Management Lessons On Risk And Project Management From The Big Dig
ISBN: 9781118115473
1st Edition
Authors: Virginia A. Greiman