You havebeenappointed project managerfor theboiler installation project andhave beenasked bytheoperations director to give a PowerPoint presentation ofthefeasi

Question:

You havebeenappointed project managerfor theboiler installation project andhave beenasked bytheoperations director to give a PowerPoint presentation ofthefeasi bility ofthis project at the next management board meeting. The presentation must provide data, charts, analysis and interpretations ofthe following:

1. Network diagram andearlystartGanttcharttoidentify thecritical path (and any near-critical activities), project startand end dates, activity floats.

2. Summary resource histograms forallproject resources to show resource conflicts in the earlystart schedule.

3. Resource smoothing andfull resource levelling options.

4. Project crashing options.